Majestic luxury apartments construction
Transparency & Progress

Project
Updates

Stay informed with regular updates on construction progress, milestones, and project developments

Latest Update

Foundation Work Completed

January 2026

We're pleased to announce the successful completion of all foundation work for Majestic Luxury Apartments. Our engineering team has verified that all structural elements meet or exceed design specifications. This milestone marks the transition to above-ground construction phases.

Foundation Complete

Structure Starting

25% Complete

Site Preparation & Permits Secured

November 2025

All necessary building permits and regulatory approvals have been obtained. Site preparation work is complete, including utility connections, drainage systems, and access roads. The project officially breaks ground with full legal authorization.

  • Building permits approved
  • Site infrastructure completed
  • Construction team mobilized

Project Launch & Pre-Sales Begin

September 2025

Majestic Luxury Apartments officially launches with strong interest from both buyers and investors. Investment fund structure finalized with legal documentation complete. Pre-sales reservation system opens for qualified buyers.

Project Timeline

Q1 2026

Foundation Phase

Q2-Q4 2026

Structure Construction

Q1-Q2 2027

Interior Finishing

Q3 2027

Project Completion